Underground Systems, Inc.

84 Business Park Drive Suite 109
Armonk, NY 10504
34 Employees

SBIR Award Summary

Total Number of Awards 10
Total Value of Awards $4.82MM
First Award Date 01/01/87
Most Recent Award Date 07/27/15

Key Personnel

Last Name Name Awards Contact
Boggs Steven A Boggs 1
Fish Larry Fish 4 Message
Alex Paul A. Alex 6 Message
Hoppe Frank Hoppe 2 Message
Zenger Walter Zenger 3 Message
Shattuck James Shattuck 1 Message
Shattuck James Shattuck 1 Message

10 Awards Won

Phase 2 SBIR

Agency: Department of Energy
Topic: 22a
Budget: 07/27/15 - 07/26/17

In order to optimize the operating efficiency of transmission systems utilities must be able to quickly restore service after a failure. Locating faults with current technologies can be a time consuming, skill and labor intensive process. Underground transmission systems are hidden from view and fault location can take sometimes days or weeks. ...

Phase 2 SBIR

Agency: Department of Energy
Topic: 57B-2014
Budget: 01/01/14 - 12/31/14

USi will leverage over 27 years of technology and applications experience in underground cable monitoring and diagnostics to implement the design of an advanced diagnostic system that detects and localizes incipient failures in pipe-type underground transmission systems caused by thermo-mechanical bending (TMB). The goal of the project is to dev...

Phase 1 SBIR

Agency: Department of Energy
Topic: 22A-2014
Budget: 01/01/14 - 12/31/14

In order to optimize the operating efficiency of transmission systems utilities must be able to quickly restore service after a failure. Locating faults with current technologies can be a time consuming, skill and labor intensive process. Underground transmission systems are hidden from view and fault location can take sometimes days or weeks. D...

Phase 2 SBIR

Agency: Department of Energy
Topic: 57 B-2011
Budget: 01/01/11 - 12/31/11

In order to optimize the operating efficiency of the underground transmission system utilities must be able to safely maximize the power cable systems capacity. This allows the operator to: (1) Establish efficient generation scheduling; (2) Maximize power transfer capability; and (3) Extend decision time and options when responding to system c...

Phase 2 SBIR

Agency: Department of Energy
Topic: 62 B-2010
Budget: 01/01/10 - 12/31/10

The

Phase 1 SBIR

Agency: Department of Energy
Topic: 57 B-2010
Budget: 01/01/10 - 12/31/10

In order to optimize the operating efficiency of the underground transmission system utilities must be able to safely maximize the power cable system

Phase 1 SBIR

Agency: Department of Energy
Topic: 2009
Budget: 01/01/09 - 12/31/09

A robust software algorithm is needed to monitors the conditions of the electricity grid in real time and use historical statistical data to predict behavior under various future conditions. The algorithm could be used release additional capacity, and improve the reliability and economic efficiency of the nation¿s transmission and distribution...

Phase 2 SBIR

Agency: Department of Energy
Topic: 2006
Budget: 01/01/06 - 12/31/06

Historically, the cost of systems that operate in real time and extract performance data from overhead transmission and distribution lines has been too high to justify widespread adaption into transmission control systems. This project will develop a low cost, wireless sensor for the real time monitoring of overhead transmission lines. The sen...

Phase 1 SBIR

Agency: Department of Energy
Topic: 2005
Budget: 01/01/05 - 12/31/05

79057S A dynamic line rating (DLR) system operates in real time and extracts maximum performance data from overhead transmission and distribution lines. Historically, the costs of such systems have been too high to justify widespread adaption into transmission control systems. This project will develop and demonstrate a low cost, dynamic overh...

Phase 1 SBIR

Agency: Missile Defense Agency
Topic: MDA87-005
Budget: 01/01/87 - 12/31/87